Construction sand

HEANG VIBOL ENTERPRISE

Investigating the potential of investment and contributing to the development of the mineral resources sector as well as increasing Cambodia’s economic status by paying taxes, providing employment opportunities to local people and supplying local sand products. Recently, Heang Vibol Company has requested to invest in a 20-hectare sand-dredging business located in the Mekong River, Geography of Koh Penc Commune, Koh Morn Commune, Kampong Siem District, Kampong Cham Province. Therefore, the company has registered in the Trade Register of the Ministry of Commerce of the Kingdom of Cambodia.
Heang Vibol is a sole proprietorship established in accordance with the laws of the Kingdom of Cambodia and has permanent residence in Cambodia (Tonle Bass Village, Tonle Bati Commune, Tbaung Khmum District, Tbong Khmum Province). The company has the capacity to build 100,000 cubic meters of sand per year. The pumps can be little changed depending on the local market’s demand for sand.
General information of the project:
– Company name: Heang Vibol
– Company headquarters: Tonlebat Village, Tonlebat Commune, Tbaung Khmum District, Tbong Khmum Province
– Business Registration Identification Number: 5374 AD
– Type: Individual limited liability company limited liability
– Stock composition: Heang Vibol
– Investment capital: 272,000 (Twenty-eight million US dollars)
– The duration of the business plan: 10 years
The concept of this investment is not for the sake of profit alone, there are many other concepts of profit, both directly and indirectly, which provide subsequent advantages, bringing prosperity to the king. The local government, as well as all the various national political economies.
In its concept of investment, the company sees many benefits that focus on the local people and the community as a whole. The concept of the project’s investment focuses on: social funds, construction potential, educational opportunities, job creation for local people, country-level revenue, and development in the local area of ​​the company.
Starting from the Company’s investment activities, the benefits of this investment are as follows:
Tax and income for Cambodia
– Create job opportunities and reduce migration of local people
– Increase the potential of materials for sand production
– Regional infrastructure improvements
– facilitating flow of water
– Increase the roadway
– Increase the quantity of fisheries
The project area is located along the Mekong River in Koh Pench Village, Koh Mith Commune, Kompong Siem District, and Village 03, Koh Sotin Commune, Koh Sotin District, Kampong Cham Province. Which is located to the east of Kompong Cham town, 4,785 kilometers and is located on the southern part of the Kyau Han bridge, 3,957 kilometers and about 105 km from Phnom Penh, along National Road 06 and National Highway 07, then travels from Kompong Cham province and runs from Kampong Cham town along the Mekong River to Koh Mate and along the Mekong River to the river town. Rights Khmom Khmom.
The project is about 1,141 meters long and 190 meters wide. The distance from Point A to Peninsula beach is about 736 meters from point B to the river bank of Doun Mao upper, about 678 meters from point C to the new shore or Koh Samrith distance. 280m away, and the distance to the river bank in the Prek Chich village is about 1,368m and the distance from D to Peninsula is about 178m.
The company’s sand deposits are located in Tonlebat village, Tonlebet commune, Tbong Khmum district, Tbong Khmum province, about 3,616 meters from the project area and 300 meters from the Kizuna bridge steeple below the project area. The stockpile is 200 meters long and 55 meters wide, which the company has leased in 10 years, with a land price of $ 1,000 a year.
The 20-hectare sand mining project has a 10-year business plan, with a total of 1,000,000 cubic meters of extraction activity. Concerning sand mining business, the company will exploit sand at a depth of between 2 meters and 3 meters, starting from the bottom of the Tonle Sap Lake in the dry season not exceeding 7 meters.
The main infrastructure construction in the project area is not as important. In the company’s sand stocks, there is no construction because it is a land lease. In addition, the company has a store or house and latrine near the sand storage area about 200 meters for workers and workers to work.
At the new sand storage site, the company has built dams for controlling the flow of water from sand mining activities into the company’s stockpiles. At the same time, the drainage system of the project is organized by a drainage pipe to bring water from the reservoir to the river.
Construction Sand Construction Patterns First, use a padded pumping machine to collect sand in the project site. The sand hole is made from a depth of 2 meters to 3 meters from the bottom of the river, which can maintain a depth of water in the dry season not exceeding seven meters into its boat.
The next phase is to stock the sand mixture in a storage area of ​​approximately 3,616 meters from the project site. After moving from the project area to the storage area and sand dredging from the boat to the sand storage site of the project.
Project activities are proposed within 10 years from 2015 to 2024. The total amount of sand is planned to be pumped every year by 100,000 m3 and the total amount of sand in 10 years to be pumped 1,000,000 cubic meters.
The project’s activities are conducted only in the daytime, divided into two main courses: between the first one from 7:00 am to 11:00 am and the second between two hours 1:00 pm to 5:00 pm. Within a year, the company operates only 300 days and the number of days it does depends on the company’s customers.
In the process of extracting sand at a site related to the company’s water use in its pattern of action is not available. Use of water only for the living of workers – workers only. For daily use, the staff is about 15 to 20 cubic meters per month used for washing and cooking. The main sources of water in this use are water supply systems.
For its drinking water, it is planned to use 20 liters of water in both the work area and its work on the boat. The average bucket of water tank is between 20-25 barrels per month. The total water consumption is 400 liters to 600 liters per month.
Based on the possibility of sand mining, the following project is a result of project costs and sand yields for 10 years.
During the 10-year period of the project, the total project revenue will be $ 317,608 and $ 252,611 and $ 206,231 respectively, with an inflation rate of 5%, 10% and 15%. The estimated cost of this estimate is estimated at $ 2.5 million per square mile and the return period for an investment of more than two years.